Refit
of vessel
as part of
life extension
Background
Extensive scope of work on refit of vessel as part of life extension, including scaffolding as well as blast and paint on 72,115m².
The Challenge
Multi-faceted project including:
- Supply, erection, dismantling 3,500 tonnes of scaffolding
- 8,000 crane lifts to move materials
- 30,000m² of environmental containment
DIS Solution
In collaboration with Qlayers, we were the first in the world to use an automated spray robot to apply 30,000m² of holding primer.
Filtered 2,500 tonnes of water from ultra-high-pressure paint removal.
Mobilised a dedicated team of over 300 people in a few weeks.
