Spanning
15 tanks in
only 9 weeks
Background
Significant volume of tank blasting and painting to undertake on docking of vessel 19,910m².
The Challenge
Complete the works spanning 15 tanks in only 9 weeks from a standing start.
Mobilise and create an experienced delivery team.
50 experienced marine blasters and painters from our commercial operation.
600 tonnes of Abrasive blast media.
13,000 litres of paint applied.
DIS Solution
Careful planning and daily progress meetings with client.
Use of very experienced workforce and management team.
Working 24/7 over the 9-week duration.
Working with client and ship to overcome issues and challenges.