Client: Babcock Marine
Location: Devonport Dockyard, Plymouth
Project: Refurbishment of dockyard caissons, flap gates and dock gates
Working as principal contractor to Babcock Marine, Denholm Industrial Services undertook a multiple asset project to refurbish a number of dry dock related water control barriers.
Services delivered:
- Scaffold access
- Containment
- Steel surface preparation
- Painting
- Mechanical and electrical works utilising Relay
The works involved preparation of substrates that were heavily contaminated with sea salts and the application of protective coatings, both above and within splash zone areas.