Denholm Industrial Logo
  • Call us on: +44 (0) 1935 420 081
  • Email us
  • Services
    • Close
    • Services
    • Scaffolding and Access
      • Close
      • Scaffolding and Access
      • Fall Prevention System
      • Plettac Metrix
    • Containment and Encapsulation
    • Metal Surface Preparation
    • Protective Coatings
    • Industrial Cleaning
    • Floor Surface Preparation
  • Sectors
    • Close
    • Sectors
    • Construction and Demolition
    • Infrastructure
    • Marine
    • Defence
    • Heritage
    • Process and Energy
    • Renewables
  • Accreditations
  • Profile
    • Close
    • Profile
    • About Us
    • Our History
    • Our Ethos
  • Case Studies
    • Close
    • Case Studies
    • Construction and Demolition
      • Close
      • Construction and Demolition
      • Beckley Court Student Accommodation
      • NatWest Tower Demolition
    • Marine
      • Close
      • Marine
      • Dockyard Water Control Barriers Refurbishment
      • Portsmouth Jetty Upgrade
      • Crane 399 Refurbishment
    • Defence
      • Close
      • Defence
      • Industrial Cleaning at BAE Scotstoun
      • New Build Offshore Patrol Vessels
      • Vanguard Class Submarines
    • Infrastructure
      • Close
      • Infrastructure
      • Bidston Moss Viaduct Strengthening
      • Bidston Moss Viaduct Metal Preparation
      • Forth Road Bridge Refurbishment
      • Vox Studios Office Fit-Out
    • Heritage
      • Close
      • Heritage
      • Clifton Cathedral Roof Covering Renewal
      • Canford Road Bridge
    • Process and Energy
      • Close
      • Process and Energy
      • First Outage at Energy from Waste Plant
  • News
  • Vacancies
    • Close
    • Vacancies
    • Scaffold Apprenticeships - Plymouth
    • Scaffolding and Access
  • Contact
    • Close
    • Contact
    • Locations
      • Close
      • Locations
      • Glasgow
      • Plymouth
      • Scunthorpe
      • Yeovil
      • SES - Birmingham
      • ALPS - Sheffield
      • Elite Scaffolding - Yeovil
    • Head Office

Bidston Moss Viaduct Metal Preparation

  1. Home
  2. Case Studies
  3. Infrastructure
  4. Bidston Moss Viaduct Metal Preparation
Client: Costain
Location: Bidston Moss, Merseyside
Project: Refurbishment of the Bidston Moss viaduct

Background

Denholm Industrial Services was contracted to provide multi-discipline services to support refurbishment of the Bidston Moss viaduct.  The viaduct was owned by three different public authorities and there were three different paint systems to remove, each with its own challenges.

The Challenge

A number of different coatings had to be removed prior to the application of the new protective coatings, with each one requiring a different approach for correct removal prior.  The coating types involved were:

  • Conventional epoxy coatings
  • Lead based primers
  • Thermal metal sprayed zinc coatings
  • Wax coatings
  • Chlorinated rubber coatings

Our Solution

Thermally sprayed metal coatings are hard and tenacious and full removal requires considerable time and materials. First, we checked that the specified protective coatings to be re-applied were compatible with the existing coatings.  Then, the areas in which the existing coating was in good condition were left in place and only the failing areas of metal coatings were removed.  This approach was agreed with Costain and written into the project specification.

The wax coatings that had been applied some years earlier presented a surface preparation problem.  Attempting to blast wax coatings is mostly unsuccessful, as the abrasive becomes embedded in the soft wax and no longer functions as it should.  To overcome this challenge, the wax coatings were firstly removed by hand scraping and solvent washing, prior to conventional blasting.

Due to the lead content of the primers, stringent health and safety control measures were deployed to protect our employees from unnecessary exposure to this toxic material and to comply with the “Control of Lead at Work Regulations”.

Being involved in the project from an early stage enabled effective project planning and Denholm Industrial Services was able to ensure that the risks were mitigated.  The project was successfully delivered with zero reportable accidents (AFR = 0.00), ahead of programme and under budget.

Additional

Case Studies

  • Bidston Moss Viaduct Strengthening
  • Bidston Moss Viaduct Metal Preparation
  • Forth Road Bridge Refurbishment
  • Vox Studios Office Fit-Out

Denholm Industrial Group

  • Flag Secondary Denholm Industrial Services
  • Denholm Flag Icon Denholm Universal
  • SES RGB SES
  • ALPS LOGO (White No Strapline) ALPS

Head Office

Denholm Industrial Services Limited
1 Barracks Close
Lufton
Yeovil
BA22 8RN
enquiries@denholm-industrial.com
+44 (0) 1935 420 081
  • Terms of Use
  • Privacy Policy
  • Cookie Policy
  • Modern Slavery Act Statement
  • Gender Pay Gap Report
Denholm Industrial Services Limited is part of The Denholm Group
Telephone: +44 (0) 1935 420 081 Email: enquiries@denholm-industrial.com
© Denholm Industrial Services Limited 2025. All rights reserved.

Website by Gecko Agency

Our site uses cookies to help give you the best online experience.
Please let us know if you are happy for us to use these cookies or if you wish minimum functionality only.

I decline